This project is located in Iraq and involves power system studies for three substations.To successfully accomplish this endeavor, we’ve diligently developed a range of key deliverables for all substations:

1.Single Line Diagram As Built in AutoCAD

2.ETAP Modelling for the following studies

a)Load flow Studies

b)Short circuit Analysis

c)Motor acceleration Studies

d)Relay coordination

e)Harmonics analysis

3.Power Systems Report & Recommendations for Complete Plant.

Congratulations to Jeyakumar and Ajith for bagging the project.