Unit Protection Study – Large Industrial Coke Processing Facility | Power Projects
Project Completed

Unit Protection Study for a Large Industrial Coke Processing Facility

Engineering Review of Protection Philosophy for a Multi-Voltage Industrial Power System — brownfield expansion and electrical system upgrade covering transformer, generator, busbar and motor feeder protection

33 kV / 11 kV / 6.6 kV / 415 V
Unit Protection Study ETAP Model Validation Transformer Protection Generator Protection Busbar Protection Brownfield Expansion 3-Week Delivery
Power Projects Coke Processing Industry Continuous-Process Facility

Power Projects was engaged to perform a Unit Protection Study for a large industrial coke processing facility as part of a brownfield expansion and electrical system upgrade.

The study focused on reviewing and validating the protection philosophy for a complex electrical distribution network supplying critical process equipment across multiple voltage levels. Unlike conventional relay coordination studies, the scope was centred on verifying unit protection schemes for major electrical assets to ensure dependable fault detection and minimise equipment damage and unnecessary outages.

The assessment was carried out using the client's ETAP simulation model, with Power Projects responsible for validating model inputs, reviewing the protection configuration, and providing engineering recommendations where required.

System Overview

The facility operates a multi-voltage industrial electrical distribution network supplying continuous-process loads.

Voltage Levels

  • 33 kV distribution system
  • 11 kV distribution system
  • 6.6 kV switchgear
  • 415 V motor control and auxiliary distribution

Electrical Assets

  • Power and distribution transformers
  • Diesel generator
  • HV switchboards and MV switchgear
  • Motor Control Centres (MCCs)
  • Power Control Centres (PCCs)
  • Power Distribution Boards (PDBs)
  • Variable Frequency Drive (VFD) panels
  • Cooling tower systems
  • Coke handling equipment
  • Electric locomotives and process machinery

The combination of multiple voltage levels and interconnected equipment results in a protection system requiring detailed engineering validation.

Study Scope

The study focused on validating the unit protection philosophy across major electrical assets in the facility.

ETAP — Client-Provided Simulation Model Used for Assessment

Review of the client-developed ETAP simulation model

Validation of electrical system data

Unit protection study across the network

Assessment of protection philosophy

Verification of transformer protection arrangements

Review of protection coverage for critical process equipment

Preparation of a Unit Protection Study Report

Note: Network modelling was excluded from the scope, as the complete ETAP model was provided by the client.

Engineering Focus Areas

1

Protection of Critical Electrical Assets

The facility includes multiple high-value transformers supplying essential process systems. Protection performance is critical, as internal faults can lead to:

  • Equipment damage
  • Production downtime
  • High replacement cost
  • Operational disruption

The study focused on ensuring that protection systems correctly distinguish between internal and external faults.

2

Multi-Voltage Electrical System

The network operates across four voltage levels — 33 kV, 11 kV, 6.6 kV and 415 V. Each voltage level requires appropriate protection settings based on system configuration, fault levels, and equipment ratings.

Ensuring consistent protection coordination across these levels was a key aspect of the review.

3

Continuous Industrial Operation

The coke processing facility operates as a continuous production system. Any unnecessary trip of transformers or major feeders can impact downstream processes and lead to significant production losses.

The protection philosophy therefore required a balance between:

  • Fast fault clearance
  • Equipment protection
  • Operational continuity
4

ETAP Model Validation

Before performing the protection assessment, the client-provided ETAP simulation model was reviewed to confirm:

  • Equipment ratings
  • Transformer configurations
  • Network representation
  • Protection input data

This ensured that the study was based on a consistent and validated system model.

Engineering Methodology

Model Review

  • Network topology
  • Transformer representation
  • Equipment connectivity
  • Protection modelling assumptions

Unit Protection Assessment

  • Transformers
  • Generator
  • Busbar protection interfaces
  • Motor feeders
  • Auxiliary distribution systems

Technical Review

  • Proper protection zoning
  • Correct application of unit protection principles
  • Reliable fault detection
  • Selective isolation of faulty equipment

The objective was to ensure protection operated only within the defined zone and remained stable during external faults. Engineering observations and recommendations were documented where improvements were identified.

Deliverables

A comprehensive Unit Protection Study Report was prepared, including:

Study methodology

ETAP model validation summary

Protection assessment results

Engineering observations

Recommendations for system improvement

Key Outcomes

The study delivered a structured evaluation of the facility's protection philosophy, resulting in:

Validation of the ETAP model used for the study

Verification of unit protection coverage across key assets

Improved confidence in transformer protection philosophy

Identification of engineering improvement opportunities

Technical documentation supporting future protection decisions

The assessment provides a solid technical basis for enhancing protection reliability and reducing the risk of equipment damage due to internal faults.

Project Delivery

The study was completed within a three-week engineering schedule following receipt of the purchase order and complete engineering inputs.

3 weeks

Engineering Schedule

Complete study delivered within three weeks of purchase order and receipt of all engineering inputs

The execution workflow included:

1

Engineering documentation review

2

ETAP model validation

3

Unit protection assessment

4

Engineering review & recommendations

5

Final report preparation & submission

Conclusion

Unit protection is critical for safeguarding high-value electrical equipment in industrial power systems, particularly in continuous-process facilities where system reliability directly impacts production.

Through this engagement, Power Projects delivered a comprehensive engineering review of the protection philosophy, validated the client ETAP model, and assessed the effectiveness of unit protection schemes across a multi-voltage industrial network operating at:

33 kV 11 kV 6.6 kV 415 V

The study provides a structured engineering foundation for future protection enhancements and supports safe, reliable, and efficient operation of the facility.

Unit Protection Study Coke Processing Facility ETAP Model Validation Transformer Protection Generator Protection Busbar Protection Motor Feeder Protection 33 kV / 11 kV / 6.6 kV Brownfield Expansion Industrial Protection Continuous Process Protection Philosophy Review

Need a Unit Protection Study for Your Industrial Facility?

Power Projects delivers comprehensive unit protection studies, ETAP model validation, and protection philosophy reviews for industrial power systems, substations, and brownfield expansion projects worldwide.

Get in Touch