Grid-Compliant Integration of a 15 MW Solar PV Project, Rajasthan | Power Projects
Project Completed

Enabling Grid-Compliant Integration of a 15 MW Solar PV Project in Rajasthan

Power Quality and Reactive Power Compensation Studies for a 15 MW Solar PV development in Jodhpur, Rajasthan — connecting a 6 MW existing facility with a new 9 MW expansion to the 132 kV RVPNL substation

15 MW Solar PV Jodhpur, Rajasthan 33 kV / 132 kV RVPNL PSCAD v5.0.2 PSS®E v36.3 IEEE 519-2022 CEA Compliant
Power Projects Grid Compliance · Power Quality Renewable Energy Integration

As renewable energy projects continue to expand in scale and complexity, grid connection studies have become a critical step in securing approvals and ensuring long-term operational reliability.

Power Projects recently completed a comprehensive suite of Power Quality and Reactive Power Compensation Studies for a 15 MW Solar PV development in Jodhpur, Rajasthan. The project combined an existing 6 MW solar facility with a new 9 MW expansion and connects to the utility network through a 33 kV interconnection linked to the 132 kV RVPNL substation.

The objective was straightforward: demonstrate that the expanded facility could operate in compliance with applicable grid requirements while maintaining acceptable power quality and voltage performance across a range of operating conditions.

The Challenge

The project presented several technical challenges that required detailed analysis before grid integration could be confidently assessed.

Most notably, the plant was connected to a relatively weak network represented by:

Network Parameters — Weak Grid Conditions

5
Short Circuit Ratio (SCR)
10
X/R Ratio

Under these conditions, inverter-based renewable generation can face increased sensitivity to voltage variations, reactive power requirements, and harmonic performance. In addition, the generating station was required to demonstrate compliance with power factor requirements ranging from 0.95 lagging to 0.95 leading while maintaining acceptable voltage levels across the network.

The assessment also needed to verify performance across multiple operating scenarios, including generation levels from 10% to 100% of plant output.

Our Approach

Using PSCAD Version 5.0.2 and PSS®E Version 36.3, Power Projects developed detailed models of the solar facility and surrounding network to evaluate both steady-state and power quality performance.

PSCAD Version 5.0.2 — EMT Simulation PSS®E Version 36.3 — Steady-State Analysis

Plant Configuration Assessed

15 MW total AC capacity
30 × 0.3 MVA inverters
9 × 0.68 MVA inverters
Four 1.4 MVA inverter duty transformers
One 0.7 MVA inverter duty transformer
Three 3 MVA inverter duty transformers
One 5 MVAr SVG system
One 0.693 MW PCS system
33 kV grid connection

Study Programme

Power Quality Assessment

  • Harmonic analysis
  • DC current injection assessment
  • Flicker analysis

Grid Performance & Reactive Power

  • Reactive power compensation studies
  • Power factor compliance verification
  • Voltage profile assessment
  • Reactive power capability verification

Results

The studies confirmed that the solar plant satisfies key technical requirements for grid connection and operation.

Harmonic Compliance

Individual harmonic current distortion levels at the 33 kV Point of Interconnection remain within specified limits. Total voltage harmonic distortion also found to be compliant.

IEEE 519-2022

DC Current Injection

0.002%

Maximum DC current injection at the POI — significantly below the permitted limit.

Limit: 0.5% (IEEE 1547-2018)

Flicker Performance

Short-term and long-term flicker assessments satisfied requirements, confirming that no additional mitigation measures were necessary.

IEC 61000

Reactive Power Capability

The plant successfully demonstrated its ability to provide reactive power equivalent to 33% of active power output in accordance with applicable CEA requirements.

CEA Requirements

Voltage Performance

Across all assessed operating conditions, bus voltages remained within the acceptable operating range.

0.9 p.u.
Min
1.1 p.u.
Max

Project Outcome

The completed studies provided the technical evidence required to demonstrate that the 15 MW Solar PV facility can:

Meet utility interconnection requirements

Comply with applicable power quality standards

Maintain acceptable voltage performance

Support network reactive power requirements

Operate reliably under weak grid conditions

Achieve regulatory compliance for grid connectivity

By combining detailed electromagnetic transient analysis in PSCAD with network modelling in PSS®E, Power Projects delivered a complete grid integration assessment supporting the safe, reliable and compliant connection of the solar facility to the Rajasthan utility network.

Whether supporting new renewable developments, plant expansions, or grid compliance assessments, our team provides the technical studies required to de-risk projects and support successful network integration.

Need Power Quality or Grid Compliance Studies for Your Solar Project?

Power Projects delivers PSCAD and PSS®E-based power quality and reactive power compensation studies for solar PV, wind, and BESS projects — harmonic analysis, flicker, DC injection, and CEA / IEEE grid compliance worldwide.

Get in Touch