The scope of this project is to identify the optimal BESS Size (PCS & Battery) based on the energy charges at various time intervals. The scope also includes providing the dispatch schedule of Solar Plant + BESS. The Project is 200 MWac Solar PV plant in Hollis Creek, United States of America.
The generated Power from the solar plant is evacuated to North American Power transmission grid. The owner consultant wish to investigate the power injected by the solarinverters in terms of hourly schedule. The initial study was carried out and a detailed report was submitted that explains the energy export in hourly basis by the system based on software simulation. The study’s methodology was developed to offer the best possible solution from a technical and commercial perspective.
We appreciate Selvakumar S for bringing such a amazing business, and congratulations to Suriya kumar for successful execution.