We bagged a project from VELLD Power System Consult Sdn Bhd

We are happy to announce that we bagged a project from VELLD Power System Consult Sdn Bhd, for Unit Protection Coordination on 50MWac Solar Power Plant, Malaysia.

The project consists of 33/132 kV substation with one number of 60 MVA, 33/132 kV step up transformer, where evacuating the power of 50MWac to TNB substation via 132kV line The scope of work is to provide protection settings for ,
• Restricted Earth Fault protection (HV/LV) with GE MCAG14 relay
• Transformer Differential protection with GE P642 relay
• Cable Differential protection with NARI PCS-931 relay
• Breaker Failure protection with Schneider Electric P821 relay
• Under voltage protection (earthing interlock) with GE P94VB relay

Congratulations to Selvakumar and Jeya Kumar , Srihari Santhosh and protection team for execution of the project.

 