The Scope of work is to perform field harmonic measurement at POC (Point of Common coupling) of 230 MW NTPC CPSU solar plant for 24hrs duration with 1sec sampling interval.
The POC of 230 MW solar plant is located at 230kV Tuticorin-II GIS PS.
Based on the field harmonic measurement analysis, We have validated the Individual and total current and voltage harmonics are within the permissible limit as per IEEE 1547.
We are proud of our team’s work and our ability to provide cost-effective solutions to our clients. Congratulations to Selvakumar S and Ajithkumar Gunasekaran G for bagging the project. Congratulations to Jeyakumar Velusamy and team for the successful execution.