We are excited to announce we have bagged a power system studies project for one of the largest Oil and Gas companies in Qatar.

Scope of work:
The scope of the project is to perform Short Circuit Studies and Protection Coordination Studies for two different units.

System Description & Challenges:
Both Plants are fed from the feeders of the 33kV sub-station. Contract demand is about 6 MW and system consists of 33 kV and 415V.
Biggest challenge is ensuring the coordination in Grid connected mode and DG mode since short circuit current available during the DG mode is much less.

Congratulations to Selvakumar and Jeyakumar for bagging the project, and Congratulations to Ajith S for the execution of the project.